This page explains how to customize the display of your schedule to make it easy to read and tailored to your needs.
Rights required : Consultation of a schedule object
Customize Columns
The left-hand table in the schedule, called WBS, can be customized to display only the information that interests you.
- Show or hide a column : Right-click on the header > Columns > Check or uncheck the desired columns.
- Reorder columns: Click on a column header and drag it to the desired location.
- To resize a column: Click on the right edge of the header and drag it.
You can display only the WBS section WBS on the left) or gantt chart on the right) using the arrows between the two sections.

Sort and filter
The new schedule allows you to sort and filter by multiple columns at the same time.
You can filter by:
You can choose to display:
Phases and milestonesPhases onlyMilestones Only
You can Hide completed phases to keep only active or upcoming items on the screen. This is helpful for staying focused on the task at hand.
You can click the X in each filter to remove it.
A dot appears to indicate when a filter is active on your schedule.
Button available Manage the Schedule View - Using the Toolbar

Sorting is performed on the header of the list of phases/milestones ( WBS section WBS the left side of the screen).
This button is used to sort :
- in ascending order on first click (down arrow)
- in descending order on the second click (up arrow)
To clear the sort: right-click on the header > Multiple Sorting > Clear Sorting.
Traveling Through Time
Zooms out the period to view the schedule in greater detail (from the year to the month, week, or day).
Button available Manage the Schedule View - Using the Toolbar
Resets the Gantt view to today's date. This is useful after navigating far into the past or future of the schedule.
Button available Manage the Schedule View - Using the Toolbar
When you hover over the Gantt chart with the mouse, a indicator appears to show you the exact date marked.
Button available Gérer l’affichage du planning - ‣
Expands the period to provide a view of the project over a longer time scale.
Button available Manage the Schedule View - Using the Toolbar
Restores the Gantt chart to its default zoom level.
Button available Manage the Schedule View - Using the Toolbar
Guideline Lines
- The "Today" row is available on the Gantt chart to instantly view the current position in the schedule. A button allows you to re-center the view this row with a single click.
- The lines
Start of the project and
End of the project allow you to view your project's deadlines.
- Modifier les dates du projet : faire un clic droit sur la timeline, puis cliquer sur
Modifier les dates du projet. Une fenêtre vous permet de changer la date de début et la date de fin du projet, sans passer par le paramétrage. Les dates ne déplacent aucune phase ni aucun jalon : si elles empiètent sur un élément existant, le boutonConfirmreste grisé. Cette modification ne s’annule pas avecCtrl+Zet vide l’historique annuler / rétablir.
Why can't I change the start or end dates of my project by moving a phase the Gantt chart?
Adjust the density and visibility
Collapses all levels to display only the first level of the structure in the WBS section WBS the left side of the screen.
Button available Manage the Schedule View - Using the Toolbar
Allows you to display more rows in the schedule to show as many phases and milestones as possible.
Button available Gérer l’affichage du planning - ‣
Expand all phases to display all levels of the structure in the WBS section WBS the left side of the screen.
Button available Manage the Schedule View - Using the Toolbar
The schedule can be displayed in full-screen mode to maximize your workspace.
Button available Manage the Schedule View - Using the Toolbar
Compare and analyze
Overlay the target schedule target the gantt chart compare planned and actual progress at a glance.
Columns are also displayed in the WBS section on the left side of the screen.
Button available Manage the Schedule View - Using the Toolbar
Displays the critical path the sequence of phases and milestones that determines the minimum project duration is highlighted in the gantt chart. This is useful for identifying at a glance the elements that, if they fall behind schedule, will directly impact the project’s end date.
Button available Gérer l’affichage du planning - ‣
Show more context
Allows you to display the labels for phases and milestones in the gantt chart. You can choose whether or not to display them, depending on the number of phases and milestones, to better visualize your schedule.
Button available Gérer l’affichage du planning - ‣
When a manager assigned to a phase milestone, their photo or initials appear directly in the gantt chart in the column manager from WBS.
You can see at a glance who is responsible for what.
Button available Gérer l’affichage du planning - ‣
Weekends are displayed on the Gantt chart and are taken into account when calculating phase durations. You can adjust your schedules with this information in mind.
Button available Gérer l’affichage du planning - ‣
Mieux se repérer
- Couleurs par état et par type : le planning affiche les couleurs d’état et de type définies par vos administrateurs.
- Phases enfants : celles d’une phase mère dépliée apparaissent sur un fond plus foncé. Vous pouvez désactiver cette option.
- Jalons : un petit drapeau les identifie dans le WBS.
- Phases d’autres projets : le filtre
Masquer les phases externesles cache. - Options d’affichage : elles sont conservées dans votre navigateur.
Beaucoup de ces options ont un raccourci clavier : voir Keyboard Shortcuts.
Dans une revue de portefeuille
Le rapport planning d’une revue de portefeuille s’affiche sur le nouveau Gantt. Chaque projet est replié : dépliez-le pour voir ses phases et ses jalons. Vous pouvez zoomer, et utiliser Unfold all and Tout replier.
Export as CSV
Un bouton de la barre d’outils exporte le planning au format CSV, avec les colonnes visibles du planning. Les formats .xlsx, .png et .pdf ne sont pas encore disponibles.
Where can I find these options?
Using the toolbar

Good to know
Are display preferences (columns, filters) shared among users?
Peut-on enregistrer et partager des vues personnalisées du planning ?
Why can't I change the start or end dates of my project by moving a phase the Gantt chart?
Learn More
Step by step: