What is plan ?
With plan , it's easy to see which resources have planned or completed activities in which phases, so you can allocate resources to projects as needed.
An allocation corresponds to a resource assigned to a phase or a project. The resource can therefore enter time completed on the project/project. phase Activity entries. project manager can define the target work to be carried out and the remaining work assigned resource.
À l'initialisation du RAF global, le reste à faire est lissé sur une plage de date (date de début d'une phase/projet ou date de planification et date de fin d'une phase/projet) en excluant les jours contenant du réalisé et du reste à faire détaillé manuel et en excluant les jours non travaillés de la ressource Ressources - Onglet Calendrier
Plan capacity
When shifting a phase, if it contains detailed RAF and following this modification the detailed RAF is no longer contained in the phase, then :
Le reste à faire détaillé manuel qui n'est plus compris entre le début et la fin de la phase est annulé.
Le reste à faire détaillé lissé est recalculé et est relissé automatiquement
En l'absence de RAFDM, une journée contient du RAFDM ou la valeur -
si le RAFG n'est pas renseigné.
There is no view for this screen.
Le nombre d'affectations affiché correspond à la somme de toutes les affectations sur une phase pour les ressources/phases sélectionnées. En effet, même si j'ai sélectionné 14 ressources, j'ai pu sélectionner d'autres ressources via le sélecteur de projet, et une ressource peut être affectée sur plusieurs phases.
The project lines/phase displayed are those for which the resource has been assigned, and for which the resource has planned from remaining work and/or completed.
Une ligne Autres affectations contient les valeurs qui soit sont masquées par les options d'affichage (Affectations avec du reste à faire ou Affectations avec du réalisé) ou qui soit contiennent du réalisé saisi en dehors des dates d'affectation. S’il n’y a pas de reste à faire détaillé mais qu’il y a du RAFG, alors le projet peut faire partie de cette ligne.
Selon le paramétrage du calendrier (EN-US), le premier jour de la semaine peut varier. Ainsi : - en affichage semaine, au survol d'une semaine le jour affiché est le dimanche, - en affichage jour, les semaines commencent le dimanche
Rights required :
Go to plan capacity (only resources with the same hierarchical level or not attached to any structure are visible, and not all resources combined, if the role is set to role hierarchical).
General actions
Edit (Click on a box at plan ) ➡️ Modification of plan capacity
Button name | Description |
---|---|
A pane appears, allowing you to select one or more resources, or even all resources. A text search can be used to find resources. | |
Here is the list of filter criteria (by default) that can be used to select items for export:
- | |
A pane appears, allowing you to select one or more projects, or even all projects. A text search can be used to find projects. 🚨The aim here is to select the resources allocated to these various projects, not the projects themselves. | |
Here is the list of filter criteria (by default) that can be used to select items for export:
- | |
This button will only display resources with remaining work for the selected projects. | |
This button will only display resources with completed for the selected projects. | |
Displays plan capacity according to selected resources đźš© If no resource is selected, then this button will be grayed out: it is no longer possible to display plan capacity | |
When plan is displayed by month or week, this button is used to display view by day.
🚨 Il est possible que la granularité d'affichage ait été paramétrée par défaut via la case | |
When plan is displayed by day or month, this button is used to display view by week.
🚨 Il est possible que la granularité d'affichage ait été paramétrée par défaut via la case | |
When plan is displayed by day or week, this button can be used to display view by month.
🚨 Il est possible que la granularité d'affichage ait été paramétrée par défaut via la case | |
Display plan in full screen mode (always in a browser tab) | |
Return to a standard view of plan , with the perimeter of plan at the top of the screen. | |
Choice between | |
Select grouping by Resource or Project | |
In the header of plan capacity: This button is used to fold all lines for all resources displayed: projects and phases. In plan capacity, at resource level: This button folds all lines for the resource: projects and phases đźš© This button can be accessed from the header line of plan capacity, on the left AND at resource level by means of the chevron. | |
In the header of plan capacity: This button unfolds all rows for all resources: projects and phases. In plan capacity, at resource level: This button unfolds all rows for the resource: projects and phases đźš© This button can be accessed from the header line of plan capacity, on the left AND at resource level by means of the chevron. | |
Header of plan capacity: Allows you to fold a level on plan capacity: fold project phases, or fold resource projects, for example. In plan capacity, at resource level: This button unfolds all lines for the resource: projects and phases. đźš© This button can be accessed from the header line of plan , on the left AND at resource level using the chevron. | |
In the header of plan capacity: Allows you to unfold a level on the plan capacity: unfold project phases, or unfold resource projects, for example. In plan capacity, at resource level: Allows you to unfold a level on plan capacity: unfold project phases, or unfold resource projects for example. đźš© This button can be accessed from the header line of plan capacity, on the left AND at resource level by means of the chevron. | |
Editing is possible on the plan capacity boxes, which correspond to a resource, a project / a phase and a day, a week or a month (depending on the display mode selected) đź’ˇData shown in bold are those that have been defined manually. Those that are not have been defined via remaining work smoothing (automatic) and have not been modified. | |
A tooltip is displayed when hovering over a project or a phase for which the resource is assigned. For projects, you can see: start date, end date and smoothing start date remaining work For phases, you can see: start date, end date and smoothing start date remaining work | |
Information is available by hovering over a box on plan :
- | |
This button lets you quickly add an assignment to a resource. It triggers a Project selection popup and Phase | |
This button takes you to the resource's activity entry screen. | |
This button is used to consult a resource's file. | |
This button is used to remove the resource from phase/from the project (not only for scheduling from remaining work), only possible if there is no completed registered for the resource.
Rights required : | |
Ce bouton permet de transférer de la charge (reste à faire) de la ressource vers une ou plusieurs autres ressources.
Droit requis : |
Voici les champs retrouvés dans cet écran :
Modification of plan capacity
La modification du reste à faire est permise sur une phase dont la date de fin est postérieure à la date de début du lissage du reste à faire global (RAFG) ou postérieure à la date du jour.
Rights required :
Lorsqu'une valeur de reste à faire est corrigée, alors les valeurs sur la même ligne (même projet/phase) sont relissées automatiquement.
Voici les champs retrouvés dans cet écran :