Once your budget has been structured, you can enter "target" values.
These values will serve as a benchmark against which to compare your project's progress.
- Go to your project.
- Go to theme
Budgets >
Summary.
- Enter a value
target
for one of your allocated budgets.Allocate budgets
- Click on
Register.
On the other hand, depending on your settings, this can have effects on different representations of your budget.
For example, your category may be set up with a strategy for copying values to representations. estimated
/Revised
and planned
.Categories
If so, your entry of target
(1) will be automatically copied into the estimated
(2) and planned
(3).
This allows representation Remaining Budget
(4) to be calculated automatically with the "realized" or "invoiced" amounts.