/Schedule project resources
Schedule project resources
/Find out if a resource is available or has remaining work
Find out if a resource is available or has remaining work
Find out if a resource is available or has remaining work

Find out if a resource is available or has remaining work

Resource scheduling is based on two key elements: the remaining work and the occupancy rate.

The occupancy rate is represented by a color code, while font styles indicate scheduling over a period (day, week, month). 👇

‣

How are colors updated in scheduling boxes?

đź’ˇ

Cell colors are not updated until the data is saved.

scheduling : color-coding in the plan
scheduling : color-coding in the plan

scheduling remaining work

The remaining work be:

  • Automatically smoothed
  • Manually modified over a period of time.

When you hover over the cells, you'll see:

  • The occupancy rate (daily, weekly, or monthly),
  • The completed.
📎

Read more : Representations of the Resources themeRepresentations of the Resources theme

scheduling : color codes in Project > Resources > schedule  remaining work
scheduling : color codes in Project > Resources > schedule remaining work
  • gray: when the dates do not match the duration of the phase before the phase begins phase after the phase ends)
  • white: when no scheduling been entered
  • dark blue: the resource is underutilized: the sum of remaining work completed work completed less than capacity from 0 to 0.33
  • Light blue: The resource is well-scheduled: the sum of remaining work completed work completed less than capacity from 0.33 to 0.66
  • Light green: The resource is very well planned: the sum of remaining work completed work completed its capacity from 0.66 to 0.99
  • dark green: the resource is perfectly scheduled: the sum of remaining work completed work completed its capacity 1
  • Red: The resource is scheduled beyond its capacity the sum of remaining work completed the capacity. The resource is completely unavailable.
  • đź’ˇ

    If the load exceeds the capacity one of the meshes, the cell—which is consolidated to a different mesh—is displayed with a red corner

When scheduling remaining work work, the assignments concerned all have detailed remaining work (day/week/month).

When hovering over the cells, the occupancy level of the resource is indicated for the day, week or month on the capacity plan , as well as for the completed cell.

For details of other assignments of the resource on other projects: click on the occupancy bar or the resource.

đź’ˇ
Tips :
  • Double-click on a cell to force a manual value equal to the smoothed value.
  • Click on Reset remaining work global to return the remaining work of a resource to 0.
  • The data in the cell appears in white if the remaining work is equal to or less than availability.
  • The data in the cell appears in black if the remaining work is equal to or greater than availability.