Delete a phase or milestone

🚨
Please note that the deletionaction is final.
🚦
Prerequisite: The phase or milestone to be deleted must not be linked to other data (resources, budget, etc.).

Rights required : Deleting an object from the scheduleDeleting an object from the schedule or Removing your objects from the scheduleRemoving your objects from the schedule

Removing a phase or milestone from a project schedule involves several steps:

  1. Go to theme PlanningPlanning of the project.
  2. Click on the contextual menucontextual menu of the phase or milestone to be deleted.
  3. Click on DeleteDelete.
  4. A pop-up window appears, requesting confirmation of deletion.

    image
  5. Click on OK to continue.
  6. RegisterRegister the updated schedule.
âś…
The phase or milestone is deleted.
image
‣

Why can't I delete a phase or milestone ?

🚨
Please note that the deletionaction is final.
🚦

Rights required :

  • Deleting an object from the scheduleDeleting an object from the schedule
  • Removing your objects from the scheduleRemoving your objects from the schedule

It is also possible that other projects in the application use this phase milestone. Check to make sure that no resources or budget before deleting it. If any are budget , remove the relevant resources or budgets.