Delete a phase or milestone

Delete a phase or milestone

🚨
Please note that the deletionaction is final.
🚦
Prerequisite: The phase or milestone to be deleted must not be linked to other data (resources, budget, etc.).

Rights required : Deleting an object from the scheduleDeleting an object from the schedule or Removing your objects from the scheduleRemoving your objects from the schedule

Removing a phase or milestone from a project schedule involves several steps:

  1. Go to theme PlanningPlanning of the project.
  2. Click on the contextual menucontextual menu of the phase or milestone to be deleted.
  3. Click on DeleteDelete.
  4. A pop-up window appears, requesting confirmation of deletion.

    image
  5. Click on OK to continue.
  6. RegisterRegister the updated schedule.
âś…
The phase or milestone is deleted.
image
‣