Shift schedule dates en masse

Shift schedule dates en masse

  1. Go to theme PlanningPlanning your project
  2. Click on the contextual menucontextual menu.
  3. Click on Shifting the schedule.
  4. A new screen appears with all the phases and milestones in the schedule.

  5. Select whether the dates to be shifted are those of the target or estimated schedule.
  6. Shift all or part of the schedule.
  7. Select a number of days offset.
  8. OR enter the number of days offset specific to phases and milestones.
  9. Note staggered dates.

  10. Click on RegisterRegister.
✅
Once registration completed, the schedule is displayed with the new dates.