- Go to theme
Planning your project
- Click on the
contextual menu.
- Click on Shifting the schedule.
- Select whether the dates to be shifted are those of the target or estimated schedule.
- Shift all or part of the schedule.
- Select a number of days offset.
- OR enter the number of days offset specific to phases and milestones.
- Click on
Register.
A new screen appears with all the phases and milestones in the schedule.
Note staggered dates.
Once registration completed, the schedule is displayed with the new dates.