A dependency can be created as soon as your schedule contains at least two schedule objects, whether these are phases or milestones.
Dependencies can be created in two ways:
From the gantt chart
- Go to
Planning of the project.
- Click and hold on the starting point of the schedule object from which the dependency starts.
- Drag to the point on the objectphase or milestone) where the dependency is to be applied and release the click.
- Click on
Register once all dependencies have been set.
Dependency is displayed in dotted lines.
From phase or milestone details
- Go to
Planning of the project.
- Click on the
contextual menu to access milestone details.
- Click on
Edit.
- Click on
Planning - Dependencies tab.
- Click on the
Add.
- Select the phase or milestone to which you wish to create a dependency and the
Type dependence and
Delay if required.
- Click on
Edit to save the milestone.
- Click on
Register.
The milestone modification window appears.
A new dependency line is displayed.
It is also possible to add an external dependency: this is a dependency external to the project. Simply repeat the same operation, but in the
External dependencies
.