/Manage project schedules
Manage project schedules
/Update a schedule
Update a schedule
Update a schedule

Update a schedule

There are two ways to update a project schedule:

  • From the schedule, with a list of phases and milestones and their properties
  • From the gantt chart

Modifying schedule objects

This involves updating properties and dates directly from the list of phases and milestones.

Each property can be modified.

  1. Go to theme PlanningPlanning of a project.
  2. Modify the WordingWording.
  3. Modify the Estimated dateEstimated date.
  4. Modify the statusstatus.
  5. Modify the TypeType.
  6. Click on RegisterRegister.
image

Modify schedule dates

It's easy to update the dates of project phases or milestones from within the Gantt. Only the dates can be modified.

  1. Go to theme PlanningPlanning of a project.
  2. Click on the milestone or phase to be modified and drag to the desired date.
  3. Click on RegisterRegister.
✅
The schedule is modified and the dates are updated automatically.
image