List of multi-project tasks
💡This screen can be accessed by clicking on the title of the blocks of homepage List of tasks
The list of multi-project tasks is displayed in two different ways at view :
Tasks are actions to be carried out for a project (or a planning object). They can be assigned to users, have a deadline, a status, a type, etc.
💡Tasks related to a particular project can be viewed. Tasks
💡This screen lists platform tasks with a meta status status different from . To display all tasks, simply select the ignored statuses in the filter criterion
Classic task list
This screen is managed by the view List of tasks
General actions
Modify en masse (multi-task selection) ➡️ batch edit tasks
Mass deletion (Multi-task selection) Rights required : Delete a task
Rights required
Name | Description |
---|---|
Display task list in full screen mode | |
Return to a standard view to-do list. | |
Used to export the task list.
The attributes displayed are those set at view (break or not...)
The file is directly downloaded and named | |
Allows quick editing of task attributes (text, date...) Rights required : Modify a task or View and modify your tasks (sender, assigned, participant) 🚩 This button appears when hovering over a task | |
Go to form to modify a product. task Rights required : Modify a task or View and modify your tasks (sender, assigned, participant) 🚩 This button appears on contextual menu of a task | |
Accesses form for duplicating a task 💡 The forms for creating task and duplicating task are similar. Rights required : Add a task 🚩 This button appears on contextual menu of a task | |
Adds a task : the task selected will appear as the task parent of the new task daughter. Rights required : Add a task 🚩 This button appears on contextual menu of a task | |
To delete a task already created Rights required : Delete a task 🚩 This button appears on contextual menu of a task | |
Allows you to quickly add a task when you've just added a new one. Rights required : Add a task |
Task list: Kanban board
💡 Maps are displayed progressively in each column at parameter as you scroll down.
💡 It's possible to quickly modify all elements of a task without consulting it - except for the project.
General actions
Modify en masse (multi-task selection) ➡️ batch edit tasks
Mass deletion (multi-task selection) Rights required : Delete a task
Rights required
Name | Description |
---|---|
Display task list in full screen mode | |
Return to a standard view to-do list. | |
This button folds the column. Only the column name will remain visible, the text will have a different orientation as there is less space to display it horizontally. Simply click on the column to unfold it. | |
Go to form to modify a product. task Rights required : Modify a task or View and modify your tasks (sender, assigned, participant) 🚩 This button appears on contextual menu of a task | |
This button allows you to select a user and assign task with a single click. A search can be performed, and the logged-in user selected. If a user has already been assigned to task, you can delete the assignment via contextual menu . Rights required : Modify a task or View and modify your tasks (sender, assigned, participant) | |
To delete a task already created Rights required : Delete a task 🚩 This button appears on contextual menu of a task |
Filter the list of multi-project tasks
Click on Save to apply the filter and Close to return to the list.
🚨 Task filters, project filters and filter criteria applied viaaction Filter are cumulative.
Creating and modifying a task
🚩 The creation and duplication forms are similar.
Creation actions
Rights required (creation)
Modification actions
Rights required (modification)
Name | Description |
---|---|
This button folds all lines: attributes in the task | |
This button unfolds all lines: attributes in the task | |
Allows you to fold a table line: certain elements are not displayed (depending on the grouping selected) | |
Unfold a table row: display certain elements (depending on the grouping selected) | |
🚩 This action concerns the field Attachment(s) This button instantly deletes the attachment attached to the task | |
🚩 This action concerns the field Attachment(s) This button is used to change information about the attachment already added. | |
🚩 This action concerns the field Attachment(s) This button is used to add a new line to the list of attachments at task, and therefore to add a new file. 🚨 A maximum size is imposed for security reasons: 10MB for each document added Message error message displayed: file "XXX.xxx" (x GB) exceeds maximum size allowed (10.00 MB) DD/MM/YY HH:MM This is a server configuration setting, default: 10MB | |
🚩 This action concerns the field Attachment(s)
You can add a document to this attachment. For example, if the attachment is labelled "Document 123", you will be able to upload a file called | |
To delete a task already created Rights required : Delete a task 🚩 This button appears on contextual menu of a task | |
This button is used to select a template . task task and insert the attributes added at template into task. 🚩 This button appears on contextual menu of a task | |
To view the task 🚩 This button is only available for editing. | |
Send task to contacts by e-mail | |
This button is used to add two fields (if not already added): - Sender - Assigned - Participants You can also deselect fields to remove them from task. | |
This button is used to add fields (if not already added): - task parent - milestone or phase - associatedrisk You can also deselect fields to remove them from task. | |
This button is used to add fields (if not already added): - Load (d/h) - Start time target - For You can also deselect fields to remove them from task. | |
This button lets you add task These attributes must be added to a template . task task You can then select a template this buttonand the attributes will be added to the task currently being created. You can also deselect attributes to remove them from task. | |
This button is used to add a field (if not already added): - Attachment(s) You can also deselect fields to remove them from task. | |
Once the comment has been written, this button is used to add the comment to task. Rights required : Creating a comment for a task 💡 It is possible to modify and delete a comment of which you are the author without having the required rights. | |
This button is used to edit a comment already added.
Once you have made your changes, click on | |
This button is used to delete a comment that has already been added Rights required : Removing a comment from a task 💡 It is possible to modify and delete a comment of which you are the author without having the required rights. |
Field name | Functional information |
The subject is the title of task It must be clear and use the right keywords. | |
This is the project to which the task will be attached.
If you are already in a project and wish to add a task, this field will already be filled in with the project name. | |
The task type can be used to categorize tasks, for example: administrative, project management, technical... | |
The task priority allows tasks to be categorized in a different way, so that high-priority tasks are completed before low-priority tasks. | |
The status of the task changes according to its completion: to be started, in progress, completed, archived... | |
This is the task start date.
By default, this is the time and date the task was created. | |
By default, this is the user who created task. However, this can be changed to select another user.
The right Using users may be required to make a modification. | |
This field is used to select a user who will perform the task. The sender and assignee can be the same person.
💡 Tasks assigned to the logged-in user can be viewed via My tasks
The right Using users may be required to make a modification. | |
This field is used to select users and mark them as participants in task. It will be easy to share task with the list of participants.
The right Using users may be required to make a modification. | |
This field is used to select another task which will be related to the task.
It is possible to link a daughter task to a phase or a milestone, different from the parent task . | |
This field is used to select one or more milestones or a phase for which the task will be associated.
When thedeadline date of the task is selected, and you choose a phase/milestone whose dates do not include that of the task,
you will receive a warning : "Thedeadline date of task is not included in the phase associated". | |
This field is used to select a risk already added to the project and associate it with task. Risks | |
This field is used to declare a date target for the start of the task | |
This field is used to declare a deadline for completion of the task.
When your phase/milestone is selected and you choose adeadline date for a task outside those of phase,
you will receive a warning : "Thedeadline date for task is not included in the associated phase ". | |
This field allows you to enter a load for the task : d/h for example.
This allows you to compare task with other tasks that would take more or less time and resources to complete. | |
The message corresponds to the text of the task, a rich type field. | |
This field is used to add a document to the task |
batch edit tasks
💡 It is not possible to mass modify tasks if the view display is set to the Kanban task board.
By selecting several tasks in the task list, you can modify certain fields to save time.
Actions
Rights required
Field name | Description |
This field is used to modify the status of tasks, which changes over time: to be started, in progress, completed, archived... | |
This field is used to select a user who will perform the tasks. The sender and assignee can be the same person.
💡 Tasks assigned to the logged-in user can be viewed via My tasks
The right Using users may be required to make a modification. | |
This field can be used to designate a user as the sender of tasks.
💡 Tasks assigned to the logged-in user can be viewed via My tasks
The right Using users may be required to make a modification. | |
This field is used to change the priority of tasks: categorize tasks and perform high-priority tasks before low-priority tasks. | |
This field is used to declare a date target for the start of tasks. | |
This field is used to declare a deadline for the completion of tasks.
When your phase/milestone is selected and you choose adeadline date for a task outside those of phase,
you will receive a warning : "Thedeadline date for task is not included in the associated phase ". | |
The task type can be used to categorize tasks, for example: administrative, project management, technical... | |
This is the project to which the tasks will be attached. | |
Select a template from task and add the attributes (not filled in) to the modified tasks.
Inserted attributes will be displayed |