Your project was created with hypothetical dates, respecting durations without knowing the actual start date.

You can update the dates afterwards and save the new schedule as target dates.

🚦
Before modifying the target schedule, check that the schedule has been saved.
  1. Go to theme PlanningPlanning of your project.
  2. Go to contextual menucontextual menu.
  3. Click on Save estimated schedule as target.
  4. A confirmation pop-up window appears.

    image
  5. Click on OK to continue editing.
  6. 🚨
    Please note that this validation is valid for registration.
âś…
The estimated schedule is now recorded as target date.