Instead of entering planned for a phase, this button lets you define planned for specific days. This button appears if the resource can enter activities.
General actions
The selection pane on the left of the screen can be used to select other resources in order to schedule their daily load.
Name | Description |
|---|---|
This button takes you to the resource's activity entry screen. | |
This button is used to consult a resource's file. | |
This button is used to assign a target load from one resource to other resources.
For example, if the target load is 25, it will not be possible to exceed this number (resource 1 = 15, resource 2 = 10).
It is possible to select resources already present on the project or to choose one of the platform's resources.
Rights required : | |
This button is used to allocate a planned load from one resource to other resources.
For example, if the planned load is 25, it will not be possible to exceed this number (resource 1 = 15, resource 2 = 10).
It is possible to select resources already present on the project or to choose one of the platform's resources.
Rights required : |
Field name | Information |
For each resource, this field is used to schedule a load for the selected phase . | |
This field cannot be modified, but sums up the week's planning for the selected resource and phase . | |
This field cannot be modified, but sums up the planning for the month for the selected resource and phase . | |
This field cannot be modified, but shows the total planned for the project as a whole (not just for the month displayed). |